At an early stage in the application for connection process, a Construction Development Agreement, which sets out the connection characteristics for each connection point in a development, may be required. Included in this agreement are:
You will need to sign and return a Construction Development Agreement if you are developing one or more of the following:
To obtain a Construction Development Agreement, please follow the application process explained on the page 'Connect a new multi-unit housing or commercial/industrial development'
At a later stage in the application process, it may be necessary for individual Connection Agreements to be signed by the individual owners/occupiers of the new units. To do this the new owner/occupiers must be registered with a supplier of their choice. However, this only applies to units with MIC greater than 29 kilvolt-amps (kVA).
Note: Construction Development Agreements are not needed for new connections to a single commercial or industrial unit.