Wind Speed

Monitoring Requirements

As the site is located at the edge of the Poolbeg Peninsula it is exposed to coastal weather conditions. In order to limit the escape of fugitive dust from the site, the planning conditions require that ‘no demolition is to take place in Wind Speeds exceeding 20km/h’. A wind monitor has therefore been set up on site to record the wind speed at all times.

Wind Monitor

Monitoring Results

July 2021

Wind speeds did not exceed the threshold during this period. Mitigation/Action: Continue to monitor.

August 1st to August 23rd 2021

Wind speeds did not exceed the threshold during this period. Mitigation/Action: Continue to monitor.